Cover spacers are important for achieving the correct concrete cover. This helps your structure last longer and prevents concrete deterioration. Make sure you get proper advice on the cover required for your project. You then decide which cover spacers you need and how many. They are available in different shapes, sizes and materials. To help you get started, we have provided a handy overview below.
Use the small concrete setting blocks under reinforcement cages for a (foundation) beam.
Available for covers from 25 to 55 mm. Use 3 blocks per 1000 mm of reinforcement cage.
Use the large concrete setting blocks as spacers under reinforcing mesh in a slab.
Available for covers from 25 to 100 mm. Use 3 blocks per 1 m2 of slab reinforcement.
Concrete cover spacers are also available with a clip or wire. Use these for walls and along the side of a reinforcement cage when making a foundation beam.
The concrete spacers for walls are recommended over duo spacers in aggressive environments (e.g. slurry pits).
Use concrete setting rails as spacers under reinforcing mesh in a slab. They are suitable for both soft and hard substrates and are always larger than 1 mesh opening. Recommended quantity: 2.5 rails per 1 m2.
Speedies are lightweight plastic floor spacers made from 100% recycled polypropylene. Thanks to the large bearing surface, the Speedie remains stable and you need fewer per square metre than with other spacers. This saves time when setting out and reduces materials in your order. Speedies are available for covers from 20 to 70 mm and are packed in quantities of 50. Working on a large floor area? Use the Speedies dropstick to place them upright without bending down.
Guideline: 1.5 Speedies per 1 m² of slab.
Fix these plastic spacers to the reinforcement cage to achieve the correct cover between the reinforcement steel and the formwork.
Use the rings with rigid formwork (timber or steel); suitable for reinforcement steel from Ø 4.0 to Ø 12.0 mm.
Use the cones with soft formwork, such as an EPS box or Powerkist; suitable for reinforcement steel from Ø 4.0 to Ø 16.0 mm.
For both, the guideline is 6 per 1000 mm of reinforcement cage.
Long line spacers are plastic spacers used under slab reinforcement. There are specific long line spacers for hard or soft substrates. They are 2000 mm long. To calculate the number required: floor area (m2) x 0.85.
These spacers are also known as wall spacers. They keep the two reinforcing mesh layers in a concrete wall at a set distance from each other and provide the correct cover between the reinforcement steel and the formwork. Suitable for reinforcement steel from Ø 4.0 to Ø 12.0 mm.
Delivery and shipping costsWe deliver daily throughout the Netherlands and Belgium. We deliver from Monday to Friday.
Shipping costsShipping costs are displayed in the order overview in the shopping cart.
Order with standard delivery timesShipping costs are shown in the order overview.
Express deliveryExpress delivery is subject to a surcharge. Depending on the size of the order, this surcharge is between € 75 and € 400 (excl VAT). After selecting Express delivery, you will immediately see what the costs are for you.
Self collection is not possible.
Free shipping for orders with a length of up to 6 meters from € 1,200 (excl. VAT) and for orders with a length of up to 12 meters from € 4,000 (excl VAT).
Wadden IslandsWe do not deliver directly to the Wadden Islands. However, we can deliver to transport companies on the mainland that will then transport the goods to the islands.
Select desired delivery dateDuring the ordering process, you can select the desired delivery date. We will do our utmost to deliver on this date. The planned delivery date will be confirmed via email.
What time will the delivery arrive?You will be informed when the order will be delivered and unloaded. One day before the delivery date you will receive a time indication if available. We do our best for a time indication, but this is not always possible.
On the day of delivery, the driver will call approximately 30 minutes before delivery. Our products are shipped via external carriers therefore unfortunately we do not have earlier information about the time of delivery.
An order may consist of multiple deliveries and be delivered by different carriers. You will receive a separate shipping confirmation for each partial delivery with the scheduled delivery date.
UnloadFrom the public road, we unload at the desired location. We do not have a truck-mounted forklift. We unload next to the truck.
If you want to unload on your own property and the truck has to enter your property to do so, any damage is at your own risk.