1.1 Start with a level sand blinding layer with a minimum diameter of 50 mm. Note the base thickness of the EPS U-foundation box:
Maximum deviation in the groundwork: 1 cm.
1.2 Set out a string line for the dimensions and place the formwork tightly along the line. Allow for a wall diameter of 100 mm. We recommend using the external dimension of the foundation as your reference. (See figure V.01)
1.3 Fit the sawn corner pieces as tightly together as possible. Secure them with 2 pegs per corner. (See figure V.02)1.4 Cut recesses for the piles directly as you install them. Leave a maximum of 2 cm of space around the pile heads.
1.5 When cutting the boxes to size, keep at least one tongue or groove edge intact. This keeps the connection strong and ensures everything fits properly.
2.1 Place concrete spacers on the base of the foundation box.
2.2 Carefully lower the reinforcement cage into the foundation box. (See figure V.03)
2.3 Fit plastic flat base spacers to the side of the cage.
2.4 Check that the spacers are correctly positioned against the formwork wall and that the cage is properly supported on the concrete spacers.
3.1 Cut the openings for service penetrations to size using a handsaw or jigsaw. (See figure V.04)
3.2 Keep the clearance around the opening as small as possible. Maximum 2 cm.
3.3 Place the sleeve/duct through the opening.
3.4 Seal the opening around the penetration with PU foam. (See figure V.05)
4.1 Backfill the ground around both sides of the formwork. This prevents movement during the pour. On the inside, allow space for the floor insulation: fill up to the top of the formwork, minus the thickness of the floor insulation.
4.2 Secure the corner pieces firmly with corner tie-wraps, 4 per corner. (See figure V.06)
5.1 Fit the floor insulation tight to the inside of the formwork. Note: the boards sit on the sand bed, not on the formwork itself.
5.2 Lay a sheet of foil over the floor insulation.
5.3 Place spacers on top of the foil.
5.4 Lay the slab reinforcement on top of the spacers.
Prevent leakage. Seal all openings with PU foam in the following places:
(See figure V.08)
At Betonstaal.nl you can order V-foundation boxes with delivery within 4 working days, starting from just 1 piece. Combine it with your reinforcing mesh and rebar for a complete foundation in a single order. View the EPS V-foundation formwork range and and add them straight to your shopping basket.
Delivery and shipping costsWe deliver daily throughout the Netherlands and Belgium. We deliver from Monday to Friday.
Shipping costsShipping costs are displayed in the order overview in the shopping cart.
Order with standard delivery timesShipping costs are shown in the order overview.
Express deliveryExpress delivery is subject to a surcharge. Depending on the size of the order, this surcharge is between € 75 and € 400 (excl VAT). After selecting Express delivery, you will immediately see what the costs are for you.
Self collection is not possible.
Free shipping for orders with a length of up to 6 meters from € 1,200 (excl. VAT) and for orders with a length of up to 12 meters from € 4,000 (excl VAT).
Wadden IslandsWe do not deliver directly to the Wadden Islands. However, we can deliver to transport companies on the mainland that will then transport the goods to the islands.
Select desired delivery dateDuring the ordering process, you can select the desired delivery date. We will do our utmost to deliver on this date. The planned delivery date will be confirmed via email.
What time will the delivery arrive?You will be informed when the order will be delivered and unloaded. One day before the delivery date you will receive a time indication if available. We do our best for a time indication, but this is not always possible.
On the day of delivery, the driver will call approximately 30 minutes before delivery. Our products are shipped via external carriers therefore unfortunately we do not have earlier information about the time of delivery.
An order may consist of multiple deliveries and be delivered by different carriers. You will receive a separate shipping confirmation for each partial delivery with the scheduled delivery date.
UnloadFrom the public road, we unload at the desired location. We do not have a truck-mounted forklift. We unload next to the truck.
If you want to unload on your own property and the truck has to enter your property to do so, any damage is at your own risk.